Orangeburg Rd. Roundabout

Print
Press Enter to show all options, press Tab go to next option

The Orangeburg Road Roundabout Project was identified and planned by Dorchester County to reduce travel delays and improve safety at the intersection of Orangeburg Road and West Butternut Road.

The intersection currently experiences congestion and delays during periods of high traffic volumes, such as weekday morning and afternoons. Traffic backs up during these peak periods, forming queues of vehicles waiting to cross the intersection. The intersection also has a history of vehicular crashes occurring. These crashes can potentially be reduced through proper intersection improvements.


Why a Roundabout?

The South Carolina Department of Transportation suggested a roundabout as the safest traffic solution for the area. In national studies, roundabouts have been found to reduce total crashes by 35%, crashes with injuries by 75%, pedestrian crashes by 40% and fatal crashes by 90%.


Funding

In order to fund this project, Dorchester County successfully obtained $1.25 million from the South Carolina State Infrastructure Bank (SCTIB) Local Agency Fund and $750,000 from the Highway Safety Improvement Program (HSIP) funds.

Local Public Agency funds are federal or state transportation funds programmed through SCDOT and made available to qualified agencies for specified projects. HSIP funds are Federal Highway Administration (FHWA) project-specific funds administered through SCDOT’s Safety Office.


Project Updates

SCDOT has formally approved the Orangeburg Road Roundabout Improvement Project.

Sealed bids were opened on October 17, 2017.

On November 2, 2017, Dorchester County received construction concurrence from the SCDOT to award the contract to Palmetto Site Services (PSS). The same day, a Notice of Award was sent to PSS requesting their bonds and their signed agreement.

A pre-construction meeting is scheduled for November 15, 2017, at which time, a Notice to Proceed date will be established. Updated November 9, 2017

Project Timeline

  1. Concept and Surveys: Completed
  2. Public Information Meeting and Comment Period: 10/16/15
  3. Right of Way plan submitted on 2/26/16
  4. Right of Way plan approval on 5/9/16
  5. NEPA approval on 2/24/16
  6. Right of Way Acquisitions: June 2016 - ongoing
  7. Final Plan submittal: December 9, 2016
  8. Final Plan approval: May 2017 
  9. Utility Relocation: Ongoing
  10. Project out for Bid: Sealed Bids opened on October 17, 2017.
  11. Construction

Orangeburg Rd Roundabout Conceptual Design

 


Project Documents

Orangeburg Rd. Roundabout Conceptual Design

SCDOT Orangeburg Rd Roundabout Environmental Assessment

Roundabout September 2015 Public Hearing handout