March 5, 2018 Drone image

Orangeburg Rd. Roundabout

Print
Press Enter to show all options, press Tab go to next option

Information on Lane Closures Due to Construction

The Orangeburg Road Roundabout Project was identified and planned by Dorchester County to reduce travel delays and improve safety at the intersection of Orangeburg Road and West Butternut Road.

The intersection currently experiences congestion and delays during periods of high traffic volumes, such as weekday morning and afternoons. Traffic backs up during these peak periods, forming queues of vehicles waiting to cross the intersection. The intersection also has a history of vehicular crashes occurring. These crashes can potentially be reduced through proper intersection improvements.


Why a Roundabout?

The South Carolina Department of Transportation suggested a roundabout as the safest traffic solution for the area. In national studies, roundabouts have been found to reduce total crashes by 35%, crashes with injuries by 75%, pedestrian crashes by 40% and fatal crashes by 90%.


Funding 

In order to fund this project, Dorchester County successfully obtained $1.25 million from the South Carolina State Infrastructure Bank (SCTIB) Local Agency Fund, $750,000 from the Highway Safety Improvement Program (HSIP) funds and $850,000 in Dorchester County Capital Funds.

Local Public Agency funds are federal or state transportation funds programmed through SCDOT and made available to qualified agencies for specified projects. HSIP funds are Federal Highway Administration (FHWA) project-specific funds administered through SCDOT’s Safety Office.


Project Updates

  1. October 17, 2017 - Sealed bids opened.
  2. November 2, 2017 - Construction concurrence received from the SCDOT to award the contract to Palmetto Site Services (PSS).
  3. November 15, 2017 - Notice to Proceed was issued.
  4. December 13, 2017 - 90 Day utility relocation widow began.
  5. January 17, 2018 - Clearing and Grubbing complete.
  6. February 6, 2018 - Utility relocation continues.
  7. March 6, 2018 - Two weeks remaining in utility relocation work.
  8. April 2, 2018 - Construction began
  9. May 16, 2018 - Paving of the Huntington Rd. realignment began
  10. May 25, 2018 - Paving of the Huntington Rd. realignment completed.


Orangeburg Rd Roundabout Conceptual Design


Project Documents

Orangeburg Rd. Roundabout Conceptual Design

SCDOT Orangeburg Rd Roundabout Environmental Assessment

Roundabout September 2015 Public Hearing handout